ArcelorMittal has spent €300 million preparing a 2 million-tonne-a-year electric arc furnace at Dunkirk in northern France and has filed permit applications. Its nearby Mardyck electrical steel plant expects to test its final lines in spring 2027.
At a glance
- The Dunkirk furnace is designed to emit about 0.6 tonnes of CO2 per tonne of steel, a third of the blast furnace route.
- The first three Mardyck electrical steel lines started in March and employ 200 people.
- Dunkirk (€1.3 billion) and Mardyck (€500 million) are ArcelorMittal's largest European investments in a decade.
Background
A blast furnace uses coal to turn iron ore into iron before it becomes steel. An electric arc furnace (EAF) instead melts scrap and reduced iron using electricity, which cuts carbon emissions sharply. Electrical steel is a special grade that is a key material for electric motors and generators.
What happened
ArcelorMittal has advanced two major investments in northern France, Eurometal and SteelOrbis reported, citing a company note. At Dunkirk it is building a 2 million-tonne-a-year electric arc furnace and a ladle furnace. About €300 million ($336 million) has already been spent preparing the site and securing equipment.
Permit applications have been filed. The results of a consultation with France's National Commission for Public Debate have been published, and a further public consultation opened on October 15.
Why the furnace matters
The new furnace is ArcelorMittal's route to lower-carbon steel in France. It will emit about 0.6 tonnes of CO2 per tonne of steel, three times less than the blast furnace route. It will run on a mix of scrap, hot briquetted iron or direct reduced iron, and pig iron.
"In Dunkirk, the milestones already reached and the work now visible demonstrate the concrete progress of our low-CO2 steel production project," said Bruno Ribo, general director of ArcelorMittal France.
The electrical steel plant
At Mardyck, the first three lines of a new electrical steel unit started in March and now employ 200 people. Two more lines, an annealing and pickling line and a reversing mill, are under construction, with first tests expected in spring 2027.
All of ArcelorMittal's European electrical steel is now made in France, at Mardyck and Saint-Chély-d'Apcher. The Dunkirk and Mardyck projects represent investments of €1.3 billion and €500 million.
Our read
Outlook: neutral. An electric furnace shifts how steel is made at Dunkirk, using more scrap and reduced iron, but does not change near-term iron ore demand much.
What to watch
- The outcome of the public consultation and permits for the Dunkirk furnace.
- First tests of the remaining Mardyck lines in spring 2027.
For information only, not investment advice.
Iron price in India
metalscost.com India reference price as of 2026-11-18.
Detailed analysis
Timeline
- 2026-10-15: A further public consultation on the Dunkirk electric arc furnace opens.
Demand Drivers
Electrical steel for motors and generators is a growing product line for ArcelorMittal in Europe.
Supply Drivers
The Dunkirk furnace will use scrap, reduced iron and pig iron instead of blast furnace iron.
What could lift prices
- Large investments signal ArcelorMittal's commitment to steelmaking in France.
- Electrical steel lines serve demand from electric motors and generators.
What could weigh on prices
- The furnace still depends on permits and the public consultation.
- Investment is focused on lower-carbon routes rather than added blast furnace capacity.
Country impact
| Country | Impact | Reason |
|---|---|---|
| France | Medium | Dunkirk and Mardyck are ArcelorMittal's largest European investments in ten years. |
Industry impact
| Industry | Effect | Reason |
|---|---|---|
| Steel Manufacturing | Positive | The furnace cuts emissions per tonne of steel to a third of the blast furnace route. |
Who gains, who loses
- Electric motor makers in Europe: They gain a European source of electrical steel.
- Blast furnace operations at Dunkirk: The EAF is ArcelorMittal's lower-carbon alternative to the blast furnace route there.
Other ways this could play out
- If permits are granted on schedule, Dunkirk could become a model for low-carbon steel in Europe.
- If the consultation raises objections, construction could slow.
Price risks
- Permit or consultation delays could hold back the furnace.
- Scrap and reduced iron supply will affect the furnace's running costs.
Technical view
Price is mixed relative to its 20-period and 50-period moving averages, showing no clear trend alignment.
Computed from metalscost.com's own stored price history.