Endeavour Mining has approved construction of its Assafou gold project in Côte d'Ivoire at a cost of about $1.2 billion, 13% more than its April estimate. First production is targeted for the first half of 2029.
At a glance
- Assafou is expected to produce an average of 320,000 ounces of gold a year in its first eight years.
- Higher land and crop compensation accounts for about 60% of the cost increase.
- Endeavour aims to lift annual output to 1.5 million ounces by 2030.
Background
Endeavour Mining is a gold producer focused on West Africa. A construction decision commits a company to build a mine after its studies. A definitive feasibility study is the detailed study used for that decision. All-in sustaining cost is the full cost of keeping a mine running, per ounce of gold produced.
What happened
Endeavour Mining approved construction of Assafou on Thursday, with first production targeted for the first half of 2029, MINING.COM and The Northern Miner reported.
The development budget rose by $139 million, or 13%, from the $1.06 billion estimate in the April feasibility study.
Endeavour has committed $58.7 million, about 5% of the revised budget. Resettlement work begins in late November, with process plant earthworks before year-end.
Why the cost rose
Higher land and crop compensation, agreed after talks with local authorities and communities, makes up about 60% of the increase. Power infrastructure accounts for about 10%.
Extra operational preparation and contingency each add about 15%, MINING.COM reported. Some costs, including grid connections and a highway diversion, are still under negotiation.
What it means
The study projects average output of 320,000 ounces a year for the first eight years, at an all-in sustaining cost of $1,026 an ounce. The mine has an initial life of 16 years.
Assafou and an underground expansion at Sabodala-Massawa in Senegal are meant to lift Endeavour's output to 1.5 million ounces a year by 2030.
"We will continue to prioritize shareholder returns while we organically grow the business," chief executive Ian Cockerill said. Lycopodium holds the engineering and construction management contract.
Our read
Outlook: neutral. A new mine due in 2029 adds future gold supply but has no near-term effect on prices.
What to watch
- The start of resettlement work in late November and plant earthworks before year-end.
- Final terms of the mining convention with Côte d'Ivoire.
- Further changes to the construction budget.
For information only, not investment advice.
Gold price in India
metalscost.com India reference price as of 2026-11-23.
Detailed analysis
Timeline
- 2026-11-12: Endeavour Mining approves construction of the Assafou gold project.
Supply Drivers
Endeavour plans to raise output to 1.5 million ounces a year by 2030.
Mining Production
Assafou is expected to produce 320,000 ounces a year from 2029.
What could lift prices
- Rising mine construction costs raise the price needed for new gold supply.
- New supply from Assafou is still more than two years away.
What could weigh on prices
- Assafou will add about 320,000 ounces a year of new gold supply from 2029.
- Miners are still approving large new projects.
Country impact
| Country | Impact | Reason |
|---|---|---|
| Côte d'Ivoire | High | Assafou will be built in the country, with resettlement starting in late November. |
| Senegal | Low | An underground expansion at Sabodala-Massawa is part of Endeavour's growth plan. |
Industry impact
| Industry | Effect | Reason |
|---|---|---|
| Gold Mining | Positive | A large new gold mine has been approved in West Africa. |
Who gains, who loses
- Local communities: Higher land and crop compensation makes up most of the cost increase.
- Endeavour shareholders: The project now costs $139 million more than estimated in April.
Other ways this could play out
- If construction stays on schedule, first gold could come in the first half of 2029.
- If costs under negotiation rise, the budget could increase again.
Price risks
- Grid connection and highway costs are not yet final.
- Lower gold prices could reduce the project's returns.