First Quantum Minerals said on October 21 that its expanded Kansanshi copper mine in Zambia will process about 27 million tonnes of ore this year, 8% more than designed. The extra capacity offsets falling ore grades while its Panama mine stays shut.
At a glance
- The new processing line was built for 25 million tonnes of ore a year.
- Kansanshi produced 181,183 tonnes of copper in 2025 and expects up to 260,000 tonnes by 2028.
- Zambia supplied about 93% of First Quantum's copper last year.
Background
First Quantum Minerals is a Canadian copper miner. Its biggest mine, Cobre Panama, has been shut since 2023, which leaves its Zambian mines carrying the company. Kansanshi, in northwest Zambia, was once Africa's largest copper mine. Ore grade is the share of metal in the rock, so lower grades mean more rock must be processed for the same copper.
What happened
First Quantum said its expanded Kansanshi plant is on track to process about 27 million tonnes of ore in 2026. That is 8% more than the 25 million tonnes a year the new line was designed to handle. The company credited strong equipment availability, use and milling performance.
The $1.2 billion expansion, called S3, was commissioned in August 2025 and reached commercial production in December. It added a new sulphide processing line, more smelting capacity and a new open pit, nearly doubling the mine's ore-milling capacity.
Why the extra capacity matters
Ore grades at Kansanshi are falling as the mine expands, so it must treat more rock to make the same amount of copper. The higher processing rate lets the plant handle large volumes of lower-grade sulphide ore, which offsets part of that decline.
Kansanshi produced 181,183 tonnes of copper in 2025, 6% more than in 2024, with the new line contributing about 25,000 tonnes. First Quantum guides for 175,000 to 205,000 tonnes this year, rising to between 230,000 and 260,000 tonnes by 2028.
What it means
Zambia supplied about 93% of First Quantum's copper last year, so Kansanshi's performance now largely sets the company's output. The mine is also central to Zambia's plan to lift national copper production to 3 million tonnes a year by 2031, from 890,346 tonnes in 2025.
Reaching that national target will need more mine expansions, new deposits and a stronger power supply. A plant running above its design capacity is one of the few quick gains available while larger projects are built.
Our read
Outlook: neutral. Higher throughput mainly offsets falling grades, and First Quantum did not change its production guidance.
What to watch
- Whether Kansanshi's 2026 output lands in the upper half of its 175,000 to 205,000 tonne guidance.
- Progress toward reopening Cobre Panama, which would reduce First Quantum's reliance on Zambia.
- Zambia's power supply, which every mine expansion in the country depends on.
For information only, not investment advice.
Copper price in India
metalscost.com India reference price as of 2026-11-18.
Detailed analysis
Timeline
- 2026-10-21: First Quantum says Kansanshi is on track to process about 27 million tonnes of ore in 2026.
Supply Drivers
Kansanshi's copper output is guided to rise from 181,183 tonnes in 2025 to between 230,000 and 260,000 tonnes by 2028.
Mining Production
Kansanshi expects to process about 27 million tonnes of ore in 2026, 8% above design capacity, to offset lower grades.
What could lift prices
- Falling ore grades mean miners must run harder just to hold output steady.
- Cobre Panama remains shut, keeping a large mine out of the market.
What could weigh on prices
- Kansanshi's output is guided to rise sharply by 2028 as the expansion ramps up.
- Zambia aims to more than triple national copper output by 2031.
Country impact
| Country | Impact | Reason |
|---|---|---|
| Zambia | Medium | Kansanshi is a key part of the country's goal of 3 million tonnes of copper a year by 2031. |
Industry impact
| Industry | Effect | Reason |
|---|---|---|
| Copper Mining | Positive | A large expansion is running above its design rate within a year of start-up. |
Who gains, who loses
- First Quantum Minerals: Extra throughput protects output while its Panama mine stays shut.
- Zambia: Higher output from its biggest mines moves the country toward its 2031 target.
- Copper bulls betting on African supply shortfalls: Kansanshi is delivering more ore through its plant than planned.
Other ways this could play out
- If grades fall faster than expected, extra throughput may only hold output flat.
- If power supply in Zambia tightens, the plant may struggle to keep running above design.
Price risks
- A fast ramp-up toward 260,000 tonnes would add more copper than the market expects.
- A restart at Cobre Panama would add a large new source of supply.
Technical view
Price is trading below both its 20-period and 50-period moving averages, a bearish alignment.
Computed from metalscost.com's own stored price history.