Ivanhoe Mines' Kamoa-Kakula complex in Congo produced 76,401 tonnes of copper in the third quarter, up about 19% from the second. Its Kipushi mine set a zinc record, but 2026 copper output is still trending toward the low end of guidance.
At a glance
- Kamoa-Kakula's copper output rose to 76,401 tonnes in Q3 from 64,328 tonnes in Q2.
- Ivanhoe expects 2026 copper output near the lower end of its 290,000 to 310,000 tonne guidance.
- Kipushi produced a record 77,147 tonnes of zinc in concentrate, up 10% on the quarter.
Background
Kamoa-Kakula is a large copper mining complex in the Democratic Republic of Congo, run by Ivanhoe Mines. It has its own smelter, which turns copper concentrate into anode, a near-pure copper slab. Ivanhoe cut its Kamoa-Kakula guidance earlier in 2026 and has been working to lift mining rates and recovery since.
What happened
Ivanhoe Mines said on October 8 that Kamoa-Kakula produced 76,401 tonnes of copper in saleable products in the third quarter. That compares with 64,328 tonnes in the second quarter.
Most of it, 61,506 tonnes, was copper anode from the on-site smelter. The rest came from 2,347 tonnes of blister copper toll-treated at the nearby Lualaba Copper Smelter, 5,645 tonnes of copper in slag concentrate and 6,904 tonnes of copper fines sold directly.
Why output rose
Ivanhoe raised mining rates by 30% to more than 700,000 tonnes a month, or about 8.5 million tonnes a year. A new box-cut access to the Kamoa 1 mine, called Kahala, is now working. After a set of plant changes known as Project 95, the Phase 1 and 2 concentrators reached a record 89% recovery. Combined recovery across all the concentrators rose to 87.6% from 87.4%.
Even so, 2026 copper output is trending toward the lower end of guidance of 290,000 to 310,000 tonnes. Higher silica in the ore also meant more copper ended up in slag concentrate than expected.
What else helped
The smelter produced a record 118,638 tonnes of sulphuric acid, a by-product it sells. Its average price roughly doubled to about $900 a tonne from about $450 in the second quarter. A 60-megawatt solar plant came fully online in September and cut diesel use for power by 40%.
At Kipushi, zinc output reached a record 77,147 tonnes in concentrate, 10% more than the previous quarter, from a record feed grade of 41.6%. Ivanhoe says Kipushi is tracking toward the upper end of its 240,000 to 290,000 tonne guidance.
Our read
Outlook: neutral. Higher output from Kamoa-Kakula adds copper supply, but full-year production is still heading for the low end of guidance. The two effects largely cancel out for prices.
What to watch
- Whether Kamoa-Kakula's fourth-quarter output keeps 2026 within its 290,000 to 310,000 tonne guidance.
- How much copper continues to report to slag concentrate because of high-silica ore.
- Sulphuric acid prices, which have become a meaningful extra source of revenue.
For information only, not investment advice.
Copper price in India
metalscost.com India reference price as of 2026-11-18.
Detailed analysis
Timeline
- 2026-10-08: Ivanhoe reports Q3 copper output of 76,401 tonnes at Kamoa-Kakula and record zinc at Kipushi.
Supply Drivers
Kamoa-Kakula added about 12,000 tonnes of copper output compared with the second quarter.
Mining Production
Mining rates at Kamoa rose 30% to more than 700,000 tonnes a month.
Refinery Output
The on-site smelter produced 61,506 tonnes of copper anode and a record 118,638 tonnes of sulphuric acid.
What could lift prices
- Kamoa-Kakula is still heading for the low end of its 2026 copper guidance.
- High-silica ore is pushing more copper into slag concentrate.
What could weigh on prices
- Quarterly copper output rose about 19% as mining rates climbed.
- Record concentrator recovery could keep output rising.
Country impact
| Country | Impact | Reason |
|---|---|---|
| DR Congo | Medium | Kamoa-Kakula lifted its copper output sharply in the quarter. |
Industry impact
| Industry | Effect | Reason |
|---|---|---|
| Copper Mining | Positive | Higher mining rates and record recovery lifted Kamoa-Kakula's output. |
| Base Metals Mining | Positive | Kipushi set a quarterly zinc output record. |
Who gains, who loses
- Ivanhoe Mines shareholders: Copper, zinc and acid output all rose in the quarter.
- Sulphuric acid buyers: The average acid price roughly doubled to about $900 a tonne.
Other ways this could play out
- If mining rates and recovery hold, fourth-quarter output could exceed the third quarter's.
- If silica levels stay high, more copper could keep reporting to slag concentrate.
Price risks
- Supply disruptions at other big copper mines would matter more for prices than Kamoa-Kakula's recovery.
- A shortfall against the low end of guidance would tighten supply further.
Historical comparison
- Q2 2026: Kamoa-Kakula produced 64,328 tonnes of copper and Kipushi a then-record 70,177 tonnes of zinc.
Technical view
Price is trading below both its 20-period and 50-period moving averages, a bearish alignment.