Gold ₹13,128.11/g ▼ -2.17% Silver ₹164.26/g ▼ -3.33% Platinum ₹4,087.25/g ▼ -5.34% Palladium ₹2,839.47/g ▼ -3.78% Rhodium ₹24,507.21/g ▼ -0.58% Copper ₹1,082.05/kg ▼ -4.46% Aluminium ₹244.40/kg ▼ -1.87% Cobalt ₹2,855.27/kg ▼ -0.03% Gallium ₹22,096.10/kg ▼ -0.03% Indium ₹58,752.64/kg ▼ -4.20% Iron Ore ₹7.72/kg ▼ -0.35% Lead ₹158.84/kg ▼ -0.47% Lithium ₹1,172.50/kg ▲ +3.05% Molybdenum ₹7,759.18/kg ▼ -0.03% Nickel ₹1,363.03/kg ▼ -2.54% Neodymium ₹11,782.45/kg ▼ -0.03% Tin ₹3,970.97/kg ▼ -0.59% Tellurium ₹10,345.57/kg ▼ -0.03% Uranium ₹17,180.43/kg ▼ -0.03% Zinc ₹307.35/kg ▼ -1.35% Crude Oil (Brent) ₹8,694.63/bbl ▼ -0.03% Crude Oil (WTI) ₹7,914.98/bbl ▼ -0.75% Gasoline ₹233.25/gal ▼ -1.73% Natural Gas ₹303.27/MMBtu ▲ +4.30%
Lithium

Lithium Americas Raises Thacker Pass Cost Estimate by 31% to $3.83 Billion

Outlook: Neutral · November 13, 2026
Lithium Americas Raises Thacker Pass Cost Estimate by 31% to $3.83 Billion

Lithium Americas raised the estimated cost of the first phase of its Thacker Pass lithium project in Nevada by 31% to $3.83 billion. It blamed higher labour, construction and logistics costs, and still targets commercial production in 2028.

At a glance

  • The revised budget adds $895 million in capital costs and about $995 million to the funding need.
  • Labour and staffing account for $645 million of the increase.
  • Mechanical completion is still targeted for late 2027.

Background

Thacker Pass in northern Nevada is a lithium project owned by Lithium Americas in a joint venture with General Motors. Its first phase is designed to make 40,000 tonnes a year of battery-grade lithium carbonate. Mechanical completion is when construction is finished and testing can start. The US Department of Energy (DOE) has lent money to the project.

What happened

Lithium Americas said on Wednesday the first phase of Thacker Pass will cost $3.83 billion, up 31%, The Northern Miner and The National reported.

The revised budget adds $895 million in capital costs and raises the funding requirement by about $995 million.

The company now expects to spend $1.7 billion to $2 billion on phase one in 2026, up from $1.3 billion to $1.6 billion.

Why costs rose

Labour and staffing account for $645 million of the increase, including $245 million for installing piping, steel and equipment. Tariffs and logistics add $100 million, and extra contingency adds $150 million.

Logistics costs were hit by rising fuel prices, shipping problems and less US fabrication capacity, The National reported. Estimated tariff exposure fell to about $60 million from an earlier $80 million to $100 million.

How it will be paid for

Lithium Americas plans to cover the gap with a $650 million contribution to the joint venture, $315 million from DOE loan reserve accounts and a $30 million cut in required reserves.

The extra money would raise its stake in the joint venture with General Motors. Ownership changes are still being finalised with GM and the DOE.

Shares fell 8.2% to C$2.47 in Toronto by mid-Wednesday, The Northern Miner reported.

Our read

Outlook: neutral. Higher costs do not delay the 2028 start, so the effect on future lithium supply is small for now.

What to watch

  • Final ownership changes in the joint venture with General Motors.
  • Progress toward mechanical completion in late 2027.
  • Further cost changes as construction reaches its peak.

For information only, not investment advice.

Lithium price in India

Current Price₹1,172.50/kg
Day Change+3.05%
Month Change-12.03%
Year Change+19.73%

metalscost.com India reference price as of 2026-11-18.

Detailed analysis

Timeline

  • 2026-11-10: Lithium Americas signs a loan amendment cutting required sustaining-capital reserves by $30 million.
  • 2026-11-11: Lithium Americas raises the Thacker Pass phase one cost estimate to $3.83 billion.

Supply Drivers

Thacker Pass phase one is designed to make 40,000 tonnes a year of battery-grade lithium carbonate from 2028.

Trade Tariffs

Tariffs and logistics added $100 million to the cost, though tariff exposure fell to about $60 million.

What could lift prices

  • Rising costs for new projects raise the price needed to bring new lithium supply.
  • Cost overruns can make other developers more cautious.

What could weigh on prices

  • The project still targets commercial production in 2028, adding new US supply.
  • Funding is in place, so the overrun does not stop construction.

Country impact

CountryImpactReason
United StatesHighThacker Pass is planned to be a major domestic source of lithium carbonate.

Industry impact

IndustryEffectReason
Lithium MiningNegativeConstruction costs for new lithium projects are rising.
EV Battery ManufacturingNeutralThe planned 2028 start for new supply is unchanged.

Who gains, who loses

  • Construction contractors and workers: Higher wage rates and more staff make up most of the cost increase.
  • Lithium Americas shareholders: Shares fell 8.2% in Toronto as the company needs about $995 million more.

Other ways this could play out

  • If construction stays on schedule, Thacker Pass could start commercial output in 2028.
  • If costs keep rising, Lithium Americas may need more funding.

Price risks

  • Further labour or logistics cost increases.
  • Changes in tariffs could alter equipment costs.

Technical view

TrendDowntrend
RSI (14)43.1
Support₹1,137.76
Resistance₹1,325.10

Price is trading below both its 20-period and 50-period moving averages, a bearish alignment.

Computed from metalscost.com's own stored price history.

Related

Metals lithium
Countries United States

Frequently Asked Questions

$3.83 billion, up 31%, adding $895 million in capital costs.

Mainly higher labour and construction costs, plus tariffs, logistics and extra contingency.

Mechanical completion is targeted for late 2027, with commercial production expected in 2028.

Reporting based on information published by The Northern Miner. Analysis and interpretation by MetalsCost.