Gold ₹13,128.11/g ▼ -2.17% Silver ₹164.26/g ▼ -3.33% Platinum ₹4,087.25/g ▼ -5.34% Palladium ₹2,839.47/g ▼ -3.78% Rhodium ₹24,507.21/g ▼ -0.58% Copper ₹1,082.05/kg ▼ -4.46% Aluminium ₹244.40/kg ▼ -1.87% Cobalt ₹2,855.27/kg ▼ -0.03% Gallium ₹22,096.10/kg ▼ -0.03% Indium ₹58,752.64/kg ▼ -4.20% Iron Ore ₹7.72/kg ▼ -0.35% Lead ₹158.84/kg ▼ -0.47% Lithium ₹1,172.50/kg ▲ +3.05% Molybdenum ₹7,759.18/kg ▼ -0.03% Nickel ₹1,363.03/kg ▼ -2.54% Neodymium ₹11,782.45/kg ▼ -0.03% Tin ₹3,970.97/kg ▼ -0.59% Tellurium ₹10,345.57/kg ▼ -0.03% Uranium ₹17,180.43/kg ▼ -0.03% Zinc ₹307.35/kg ▼ -1.35% Crude Oil (Brent) ₹8,694.63/bbl ▼ -0.03% Crude Oil (WTI) ₹7,914.98/bbl ▼ -0.75% Gasoline ₹233.25/gal ▼ -1.73% Natural Gas ₹303.27/MMBtu ▲ +4.30%
Aluminium

Rio Tinto Tests a 360 MWh Heat Battery for Cleaner Steam at Its Yarwun Alumina Refinery

Outlook: Neutral · October 22, 2026
Rio Tinto Tests a 360 MWh Heat Battery for Cleaner Steam at Its Yarwun Alumina Refinery

Rio Tinto and US start-up Rondo Energy have begun engineering design for a 360 MWh heat battery at the Yarwun alumina refinery in Queensland. It would store cheap midday solar power as heat and supply round-the-clock steam, replacing some fossil fuel.

At a glance

  • Australia's renewable energy agency, ARENA, is paying A$3.6 million for the design stage.
  • ARENA has set aside up to A$38 million to build the battery if the study succeeds.
  • It would be a world first for heat-battery technology in the alumina industry.

Background

Alumina is the white powder refined from bauxite ore and then smelted into aluminium. Refining it needs large amounts of high-pressure steam, which is usually made by burning fossil fuels. A heat battery stores electricity as very high temperature heat and releases it later, so a plant can run on power bought when it is cheapest.

What happened

Rondo Energy and Rio Tinto have started front-end engineering and design work on a 360 MWh heat battery with 30 MW of discharge at Yarwun, near Gladstone in Queensland, the companies said. It would be Australia's largest thermal energy storage project.

The Australian Renewable Energy Agency (ARENA) is providing an initial A$3.6 million for the design study. It has committed up to A$38 million more for deployment if the study succeeds, plus up to A$33.3 million of conditional support for risks such as cost overruns and electricity prices.

How a heat battery works

Rondo's battery charges with low-cost midday electricity and stores the energy as heat in refractory brick. It then releases that heat around the clock as steam, fed straight into the refinery's existing steam network.

Australia regularly has four to six hours of surplus solar power in the middle of the day, Mining Weekly reported. Industrial plants need heat 24 hours a day, so storing cheap midday power as heat bridges that gap.

What it means

Rio Tinto says the study will show whether the technology can supply part of Yarwun's steam on a technically and economically viable basis. Neither company has said how much fuel or emissions the battery would replace.

If it works, the project would be one of the world's first large-scale uses of thermal storage for industrial heat, and a first for alumina refining. Rio Tinto's Armando Torres said generating high-pressure steam is one of the most complex parts of cutting emissions from refining.

Our read

Outlook: neutral. This is an early-stage energy study that does not change alumina or aluminium supply.

What to watch

  • The result of the design study, which decides whether ARENA's A$38 million for deployment is released.
  • Any figures from Rio Tinto on how much of Yarwun's steam the battery could supply.

For information only, not investment advice.

Aluminium price in India

Current Price₹244.40/kg
Day Change-1.87%
Month Change-6.38%
Year Change+8.13%

metalscost.com India reference price as of 2026-11-18.

Detailed analysis

Timeline

  • 2026-10-21: Rondo Energy and Rio Tinto announce engineering design work on a heat battery at Yarwun.

Supply Drivers

Energy is a major cost in alumina refining, and cheaper steam could help refineries stay competitive.

Government Policies

ARENA is funding the study and could fund deployment, showing government support for cutting emissions in heavy industry.

What could lift prices

  • Energy costs remain a pressure on refiners, as ARENA's cover for electricity-price risk shows.
  • Projects like this show producers spending to keep older refineries running.

What could weigh on prices

  • Cheaper steam from stored solar power could lower refining costs over time.
  • The project does not change alumina output, so it adds no supply pressure either way.

Country impact

CountryImpactReason
AustraliaLowThe project tests whether surplus solar power can decarbonise heavy industry.

Industry impact

IndustryEffectReason
Aluminium Smelting & RefiningPositiveRefineries could gain a path to cleaner, cheaper steam.
Energy StoragePositiveA large industrial test case for thermal storage.

Who gains, who loses

  • Rondo Energy: Yarwun would be a large reference project for its heat batteries.
  • Rio Tinto: It could cut Scope 1 emissions at Yarwun with government support.
  • Fossil fuel suppliers to the refinery: Part of Yarwun's steam could come from stored electricity instead of fuel.

Other ways this could play out

  • If the study shows good economics, deployment funding of up to A$38 million is released.
  • If electricity costs rise, the contingency support may be needed or the project could stall.

Price risks

  • The study could fail, leaving Yarwun's energy use unchanged.
  • Any effect on alumina costs is years away.

Technical view

TrendDowntrend
RSI (14)23.3
Support₹244.40
Resistance₹267.34

Price is trading below both its 20-period and 50-period moving averages, a bearish alignment.

Computed from metalscost.com's own stored price history.

Related

Metals aluminium
Countries Australia
Products Alumina

Frequently Asked Questions

A system that stores electricity as high-temperature heat in brick and releases it later as steam or hot air for industrial use.

A$3.6 million for the design study, up to A$38 million for deployment and up to A$33.3 million of conditional contingency support.

Reporting based on information published by Mining Weekly. Analysis and interpretation by MetalsCost.

← Back to News