Gold ₹12,462.98/g ▲ +0.00% Silver ₹148.33/g ▲ +0.00% Platinum ₹3,858.64/g ▲ +0.00% Palladium ₹2,653.75/g ▲ +0.00% Rhodium ₹24,310.82/g ▼ -0.56% Copper ₹1,027.54/kg ▲ +0.61% Aluminium ₹239.46/kg ▲ +0.00% Cobalt ₹2,832.39/kg ▲ +0.00% Gallium ₹21,888.98/kg ▲ +0.00% Indium ₹56,936.64/kg ▲ +0.00% Iron Ore ₹7.66/kg ▲ +0.00% Lead ₹155.67/kg ▲ +0.00% Lithium ₹1,157.08/kg ▲ +0.00% Molybdenum ₹7,686.45/kg ▲ +0.00% Nickel ₹1,299.62/kg ▲ +0.00% Neodymium ₹11,672.00/kg ▲ +0.00% Tin ₹3,552.71/kg ▲ +0.00% Tellurium ₹10,248.60/kg ▲ +0.00% Uranium ₹16,819.24/kg ▲ +0.00% Zinc ₹294.37/kg ▲ +0.00% Crude Oil (Brent) ₹8,579.27/bbl ▲ +0.00% Crude Oil (WTI) ₹7,738.76/bbl ▼ -0.03% Gasoline ₹230.93/gal ▲ +0.00% Natural Gas ₹316.18/MMBtu ▼ -0.39%
Silver

Vizsla Silver Delays First Production at Its Panuco Project in Mexico by a Year to 2028

Outlook: Neutral · November 20, 2026
Vizsla Silver Delays First Production at Its Panuco Project in Mexico by a Year to 2028

Vizsla Silver has pushed back first production at its Panuco silver-gold project in Mexico to the second half of 2028 from the second half of 2027. It is preparing a phased return to the site after 10 workers were abducted and killed.

At a glance

  • About half of the engineering is complete and about 85% of planned plant equipment has been ordered.
  • Vizsla has committed US$5 million to a foundation for communities in Sinaloa.
  • The company has not yet made a production decision for Panuco.

Background

Panuco is a silver-gold project in Sinaloa state, Mexico. A feasibility study is the detailed study used to judge whether a mine is worth building. A production decision is a company's formal choice to build it. An environmental impact assessment is the study a regulator reviews before a project can go ahead.

What happened

Vizsla Silver now targets first silver at Panuco in the second half of 2028, a year later than planned, the company said on Thursday. It said the new schedule reflects its expectations for permitting, site readiness and construction timing.

M3 Engineering has completed about half of the engineering work. About 85% of the process plant equipment planned for the project has been ordered.

Why the project slipped

Gunmen abducted Vizsla workers in Concordia, Sinaloa, on January 23, and 10 were killed, The Northern Miner reported. The company suspended some work at and near the site while engineering continued remotely.

Vizsla is working with Mexican federal authorities and security advisers on a phased return to the site. Panuco also still needs federal approvals, including its environmental impact assessment and a land-use change permit.

What it means

Apart from the timeline, Vizsla did not change the operating, capital or economic figures in its November 2025 feasibility study. That study assumed silver at US$35.50 an ounce and gold at US$3,100.

Vizsla shares fell 2.3% to C$4.16 in Toronto on Thursday morning, The Northern Miner reported. For silver buyers, new supply from Panuco now arrives a year later.

Vizsla has committed US$5 million to a foundation for Sinaloa communities and plans to direct a share of future profits to it.

Our read

Outlook: neutral. The delay pushes back new silver supply by a year, but Panuco was not producing, so current supply is unchanged.

What to watch

  • The timing of a phased return to the Panuco site.
  • Mexico's decision on the environmental impact assessment and land-use permit.
  • Award of the main mining contract and a production decision.

For information only, not investment advice.

Silver price in India

Current Price₹148.33/g
Day Change+0.00%
Month Change-24.31%
Year Change-9.11%

metalscost.com India reference price as of 2026-11-23.

Detailed analysis

Timeline

  • 2026-01-23: Gunmen abduct Vizsla workers in Concordia, Sinaloa.
  • 2026-11-19: Vizsla moves first silver at Panuco to the second half of 2028.

Government Policies

Panuco still needs an environmental approval and a land-use change permit.

Geopolitical Risks

Security in Sinaloa has disrupted work after 10 workers were abducted and killed.

Mining Production

First silver at Panuco moves to the second half of 2028 from the second half of 2027.

What could lift prices

  • The delay pushes back new silver supply by a year.
  • Security risks in Sinaloa could slow other projects too.

What could weigh on prices

  • Panuco was not yet producing, so current silver supply is unchanged.
  • Most plant equipment has already been ordered, so the project is still moving ahead.

Country impact

CountryImpactReason
MexicoHighThe project is in Sinaloa, where security problems have disrupted work.
CanadaLowVizsla is listed in Toronto, where its shares fell.

Industry impact

IndustryEffectReason
Silver MiningNegativeA new silver mine moves a year further out.

Who gains, who loses

  • Communities in Sinaloa: Vizsla has committed US$5 million to a foundation for them.
  • Vizsla shareholders: The shares fell 2.3% in Toronto on Thursday morning.

Other ways this could play out

  • If the return to site goes smoothly and permits arrive, Panuco could meet the 2028 target.
  • If security or permits slip again, first silver could move later still.

Price risks

  • Security conditions in Sinaloa remain a risk to the timeline.
  • Federal approvals are still pending.

Technical view

TrendDowntrend
RSI (14)0.4
Support₹148.33
Resistance₹196.20

Price is trading below both its 20-period and 50-period moving averages, a bearish alignment.

Computed from metalscost.com's own stored price history.

Related

Metals silvergold
Countries MexicoCanada
Industries Silver Mining
Companies Vizsla Silver

Frequently Asked Questions

Vizsla now targets first silver in the second half of 2028, a year later than its earlier target.

Vizsla cited permitting, site readiness and construction timing, as it plans a phased return after 10 workers were killed.

No. The company has not yet made a production decision for Panuco.

Reporting based on information published by The Northern Miner. Analysis and interpretation by MetalsCost.