Gold ₹14,922.60/g ▲ +0.00% Silver ₹226.02/g ▲ +0.00% Platinum ₹5,271.32/g ▲ +0.89% Palladium ₹3,624.95/g ▲ +0.70% Rhodium ₹25,404.53/g ▲ +0.22% Copper ₹1,272.59/kg ▲ +1.24% Aluminium ₹271.94/kg ▼ -0.20% Cobalt ₹3,436.35/kg ▲ +0.22% Gallium ₹22,783.48/kg ▲ +0.22% Indium ₹68,743.27/kg ▲ +0.22% Iron Ore ₹8.02/kg ▼ -0.59% Lead ₹162.46/kg ▼ -0.20% Lithium ₹1,607.94/kg ▲ +0.22% Molybdenum ₹8,124.80/kg ▲ +0.22% Nickel ₹1,359.59/kg ▼ -0.27% Neodymium ₹12,406.51/kg ▲ +0.22% Tin ₹4,771.16/kg ▲ +0.24% Tellurium ₹10,455.52/kg ▲ +0.22% Uranium ₹17,323.43/kg ▲ +0.25% Zinc ₹324.57/kg ▲ +0.18% Crude Oil (Brent) ₹9,873.16/bbl ▲ +2.04% Crude Oil (WTI) ₹8,788.78/bbl ▲ +1.27% Gasoline ₹319.01/gal ▲ +1.52% Natural Gas ₹292.65/MMBtu ▲ +1.41%
Zinc

Indonesia's Supreme Court Revoked This High-Grade Zinc Mine's Permit, But the $245 Million Project Isn't Stopping

Outlook: Bullish · September 15, 2026
Indonesia's Supreme Court Revoked This High-Grade Zinc Mine's Permit, But the $245 Million Project Isn't Stopping

Indonesia's Supreme Court revoked the environmental permit for the high-grade Dairi zinc-lead mine over earthquake risk to its tailings dam, but the mine's Chinese-backed developers say the $245 million project continues regardless.

At a glance

  • Indonesia's Supreme Court ordered the Dairi zinc-lead mine's environmental permit revoked on August 12, 2024, citing failed governance, inadequate community consultation, and unacceptable earthquake risk.
  • The deposit was estimated in 2011 at roughly 25 million tonnes grading 10.1% zinc, with some zones as high as 11.5% -- among the highest-grade zinc deposits identified anywhere.
  • Ownership sits at 51% China Nonferrous Metal Mining (through its NFC subsidiary) and 49% Bumi Resources Minerals, an Indonesian coal-mining subsidiary.
  • The World Bank Group's Compliance Advisor Ombudsman warned in July 2022 that failure of the project's proposed tailings dam was "almost certain," threatening several thousand downstream villagers in a region that experiences roughly 41 earthquakes a year.

What happened

One of the highest-grade zinc deposits ever identified is still not a producing mine, and Indonesia's top court just made that harder to change. On August 12, 2024, Indonesia's Supreme Court ordered the revocation of the environmental permit for the Dairi Prima Mineral project, an underground zinc-lead mine in North Sumatra's Dairi Regency. The court found that the Ministry of Environment and Forestry had failed to implement good governance in approving the permit, that consultation with affected communities had been inadequate, and that the mine's location on an active tectonic fault -- a region that experiences roughly 41 earthquakes a year -- posed unacceptable disaster risk.

The deposit itself is why the project has kept moving despite that history. Discovered in the late 1990s during exploration for gold and other base metals, Dairi was estimated by 2011 to hold approximately 25 million tonnes of ore grading 10.1% zinc, with some zones running as high as 11.5% -- figures that put it among the richest zinc deposits found anywhere in the world. A collapse in global metal prices in 2013 slowed the project's economics, but by 2017 Indonesia had granted a production permit, and the project's ownership had settled into its current structure: China Nonferrous Metal Mining, through its NFC subsidiary, holds 51%, with Indonesian coal miner Bumi Resources' subsidiary, Bumi Resources Minerals, holding the remaining 49%.

The legal fight over the environmental permit only began after Indonesia issued a fresh one in August 2022. Eleven residents near the mine challenged it in February 2023; the Jakarta State Administrative Court sided with them that August, ordering it revoked; a higher administrative court reversed that decision in November 2023; and the Supreme Court then restored the original revocation in August 2024. NFC's response, according to reporting from the Business & Human Rights Resource Centre, was that the ruling "might affect the project's progress" but that the project would continue nonetheless -- and there is no confirmed indication Indonesia's environment ministry has enforced the revocation since.

The details

A 10-to-11.5% zinc grade is the kind of number that gets a deposit built almost anywhere else. Most zinc mines operating today process ore running in the low single digits to perhaps 8% or 9%; a deposit consistently above 10%, confirmed across roughly 25 million tonnes, represents an unusually concentrated and economically attractive resource. That grade is exactly why Dairi has stayed alive through a metals-price collapse, a change in Indonesian permitting requirements, and now a decade of litigation -- the underlying rock is rich enough that its backers keep finding it worth pursuing regardless of the above-ground obstacles.

Those obstacles center on a single piece of infrastructure: the tailings dam that would store the mine's waste rock and processing residue. Tailings dams fail when the material holding them together loses structural integrity, and earthquakes are one of the most common triggers -- shaking can liquefy the packed waste behind a dam wall, turning a solid structure into a slurry that breaches its containment and flows downhill. In a region recording roughly 41 tremors a year, the World Bank Group's Compliance Advisor Ombudsman -- an independent watchdog that investigates complaints against World Bank Group-linked private-sector lending -- did not treat this as a remote risk. Its July 2022 appraisal concluded a failure was "almost certain" and could produce irreversible harm to thousands of villagers living downstream, people who hold no equity stake in the mine and would absorb the disaster's cost regardless of who owns the project when it happens.

What happened next is itself a lesson in how little a single ruling settles in a live permitting dispute. Indonesia issued the project a fresh environmental permit in August 2022, weeks after the CAO's warning. Residents challenged it, won at the state administrative court, lost that win on appeal, and then won again -- decisively, at the Supreme Court -- two years later. Four reversals across two years, ending in the country's highest court, is not a sign of a settled legal question; it is a sign of how much institutional friction even a clear-cut disaster-risk finding has to survive before it translates into an enforced outcome. NFC's own public response -- that the ruling "might affect the project's progress" rather than that it would halt the project -- suggests the company itself is treating the Supreme Court's order as one more obstacle to manage rather than a final word.

The financing side of the story reinforces that reading. CNIC Corporation, a state-owned investment vehicle controlled by China Reform Holdings Corporation, delivered $245 million to the project around the same month residents were demonstrating outside the Chinese embassy over exactly the risks the CAO had documented two years earlier. When a human rights research group sought comment from CNIC, NFC and China Reform Holdings Corporation about the community's concerns, all three declined to respond. Capital continuing to flow into a project with an active, top-court-level legal cloud and a documented catastrophic-risk warning is itself informative for anyone assessing how mining-investment risk actually gets priced in practice -- geological wealth and legal jeopardy are evidently not treated as mutually exclusive by the parties who stand to profit if the mine is eventually built.

Why it matters

For anyone tracking global zinc and lead supply, Dairi is a reminder that a rich deposit on paper is not the same as tonnage that will actually reach a smelter -- one of the highest-grade zinc discoveries in the world has now spent close to three decades moving between exploration, permitting and litigation without producing a single tonne. For India, which is pursuing its own aggressive push into critical-minerals mining and has its own experience balancing foreign investment against community and environmental review, Dairi is also a case study in a subtler risk: even a country's highest court ruling against a project does not automatically mean the project stops, if the ministries responsible for enforcement and the companies bankrolling it are not aligned with that ruling.

Our read

Outlook: bullish. Dairi's continued permitting and legal limbo keeps roughly 25 million tonnes of unusually high-grade zinc-lead ore off the near-term global supply map, a mild structural argument for tighter zinc-lead concentrate availability. Confidence is kept low because this is a long-running, slow-moving story rather than a near-term price catalyst, and a resolution in either direction -- continued delay or eventual production -- would take years to materially affect global supply.

What to watch

  • Whether Indonesia's Ministry of Environment and Forestry actually enforces the Supreme Court's August 2024 revocation order or allows the project to continue under its prior permit status.
  • Any updated tailings-dam design or independent seismic risk assessment published for the Dairi site.
  • Further financing, ownership, or contractor changes involving China Nonferrous Metal Mining, Bumi Resources Minerals, or CNIC Corporation.
  • Community and rights-group responses, given the project's history of unanswered inquiries directed at CNIC, NFC, and China Reform Holdings Corporation.

For information only, not investment advice.

Zinc price in India

Current Price₹324.57/kg
Day Change+0.18%
Month Change-3.28%
Year Change+32.74%

metalscost.com India reference price as of 2026-10-03.

Detailed analysis

Timeline

  • 1998-01-01: The Dairi zinc-lead deposit is discovered in North Sumatra during exploration for gold and other base metals.
  • 2011-01-01: A reserve estimate puts the deposit at approximately 25 million tonnes grading 10.1% zinc, with some zones as high as 11.5% -- among the highest-grade zinc deposits identified globally.
  • 2013-01-01: A collapse in global metal prices disrupts the project's economics.
  • 2017-01-01: Indonesia grants a production permit for the project; ownership settles at 51% China Nonferrous Metal Mining (via its NFC subsidiary) and 49% Bumi Resources Minerals.
  • 2022-07-13: The World Bank Group's Compliance Advisor Ombudsman releases a compliance appraisal warning that failure of the project's proposed tailings dam is "almost certain," threatening several thousand downstream villagers.
  • 2022-08-01: Indonesia's Ministry of Environment and Forestry issues a new environmental permit for the project.
  • 2023-02-01: Eleven residents near the mine file a legal challenge against the environmental permit.
  • 2023-08-01: The Jakarta State Administrative Court rules in favor of the residents, ordering the permit revoked.
  • 2023-11-01: A higher administrative court reverses the ruling, reinstating the permit.
  • 2024-06-11: Residents from Dairi Regency protest outside the Chinese embassy in Jakarta over the project's seismic and environmental risks.
  • 2024-06-24: CNIC Corporation, NFC and China Reform Holdings Corporation are contacted for comment on the community's concerns and the reported $245 million in project financing; none responds.
  • 2024-08-12: Indonesia's Supreme Court restores the lower court's ruling, ordering the environmental permit revoked and finding the ministry failed to implement good governance.
  • 2026-09-13: An opinion piece on Eurasia Review revisits the Dairi saga as a case study in mining investment risk and the cost of getting project development wrong.

Supply Drivers

The Dairi deposit's roughly 25 million tonnes at 10.1% zinc (up to 11.5% in some zones) remains undeveloped nearly three decades after discovery, illustrating that some of the highest-grade zinc-lead resources identified globally are not straightforward, near-term additions to world mine supply once permitting and community-risk disputes intervene.

Government Policies

Indonesia's Ministry of Environment and Forestry approved a new environmental permit for the Dairi project in August 2022, only for the Supreme Court to order it revoked on August 12, 2024, finding the ministry had failed to implement good governance and had not adequately consulted affected communities -- a sequence that shows a real gap between a ministry's permitting decision and what the country's own courts consider lawful.

Geopolitical Risks

The project is majority-owned by China Nonferrous Metal Mining through its NFC subsidiary and was financed with $245 million from CNIC Corporation, a state-owned investment vehicle controlled by China Reform Holdings Corporation -- Chinese state-linked capital continuing to back a project even after Indonesia's Supreme Court ordered its environmental permit revoked.

Mining Production

Dairi was estimated in 2011 to hold approximately 25 million tonnes of ore grading 10.1% zinc, with some zones as high as 11.5% -- among the highest-grade zinc deposits identified globally -- but the project has not reached production despite a 2017 production permit, owing to the unresolved environmental-permit litigation.

What could lift prices

  • Continued legal and regulatory limbo keeps roughly 25 million tonnes of 10.1%-11.5% grade zinc-lead ore off the near-term global supply map, a modest structural support for zinc-lead concentrate availability for as long as the dispute remains unresolved.
  • Financing has continued despite the legal setback -- CNIC Corporation's $245 million commitment around June 2024 came after, not before, the World Bank Group watchdog's catastrophic-risk warning -- suggesting the project's backers still see long-run economic value in eventually advancing it.

What could weigh on prices

  • If Indonesian authorities and the project's backers eventually resolve the permitting standoff, the roughly 25-million-tonne deposit could still add meaningful new zinc-lead concentrate supply over time.
  • The dispute has already run more than a decade without resolution, meaning any eventual production addition remains distant enough that it exerts little near-term influence on global zinc or lead pricing.

Country impact

CountryImpactReason
IndonesiaHighThe Dairi mine sits in Indonesia's North Sumatra province, and the country's own courts, ministries and communities are the direct parties to the permitting dispute that has stalled one of the world's highest-grade zinc deposits.
ChinaMediumChinese state-linked entities hold majority ownership of and financing exposure to the project, continuing to back it even after Indonesia's top court ruling.

Industry impact

IndustryEffectReason
MiningNegativeA decade of reversing court rulings, a World Bank Group watchdog's catastrophic-risk finding, and continued financing despite a Supreme Court revocation together illustrate the kind of prolonged permitting and community-risk exposure that raises the cost and uncertainty of developing even exceptionally rich ore deposits.

Who gains, who loses

  • China Nonferrous Metal Mining and the project's financing backers: Majority ownership through NFC's 51% stake, plus continued financing from CNIC Corporation, positions them to capture the economic upside of an exceptionally high-grade deposit if the project is eventually built.
  • Communities downstream of the proposed tailings dam in Dairi Regency: The World Bank Group's Compliance Advisor Ombudsman found a tailings dam failure "almost certain" in this seismically active region, threatening several thousand villagers who hold no ownership stake in the project and would bear the disaster's cost if it occurred.

Other ways this could play out

  • If Indonesia's environment ministry actually enforces the Supreme Court's August 2024 revocation, the project could face years of further delay or a requirement to redesign its tailings-dam plan around the site's seismic risk.
  • If NFC and its partners proceed regardless, as the company has indicated, the project could continue moving toward production despite the unresolved legal cloud, testing how strictly Indonesia enforces its own top court's rulings against a foreign-backed investment.
  • If a significant seismic event were to strike the region before a safer tailings design is in place, the risk the CAO and Supreme Court both flagged could shift from a documented possibility to a realized disaster.

Price risks

  • A prolonged halt or outright cancellation of the Dairi project would keep a confirmed high-grade zinc-lead reserve off the market indefinitely, a modest long-run supportive factor for global concentrate supply.
  • A disorderly resolution -- through renewed community protest, a tailings-related incident, or a dispute over the Chinese financing -- could disrupt the project on a timeline outside any party's current control.

Historical comparison

  • 2022-2024 permitting and legal history: The Dairi environmental permit was granted, revoked by a lower administrative court, reinstated on appeal, and finally revoked again by Indonesia's Supreme Court -- four reversals in roughly two years, illustrating how unsettled the project's legal status remained even after each individual ruling.

Technical view

TrendSideways
RSI (14)20.0
Support₹323.97
Resistance₹350.02

Price is mixed relative to its 20-period and 50-period moving averages, showing no clear trend alignment.

Computed from metalscost.com's own stored price history.

Related

Metals zinclead
Countries IndonesiaChina
Industries Mining

Frequently Asked Questions

It is an underground zinc-lead mine being developed in Dairi Regency, North Sumatra, Indonesia, built around a deposit estimated in 2011 at roughly 25 million tonnes grading 10.1% zinc, with some zones as high as 11.5% -- among the highest-grade zinc deposits identified anywhere in the world.

On August 12, 2024, the court found that the Ministry of Environment and Forestry had failed to implement good governance in approving the project's environmental permit, that community consultation was inadequate, and that the mine's location on an active tectonic fault -- a region recording roughly 41 earthquakes a year -- posed unacceptable disaster risk.

China Nonferrous Metal Mining holds 51% through its NFC subsidiary, and Indonesian coal miner Bumi Resources' subsidiary, Bumi Resources Minerals, holds the remaining 49%. CNIC Corporation, a Chinese state-owned investment firm, has also provided $245 million in project financing.

According to reporting from the Business & Human Rights Resource Centre, NFC has said the Supreme Court's ruling "might affect the project's progress" but that the project will continue regardless, and there is no confirmed indication Indonesia's environment ministry has enforced the revocation since the August 2024 decision.

Reporting based on information published by Eurasia Review. Analysis and interpretation by MetalsCost.

← Back to News