Gold ₹13,128.11/g ▼ -2.17% Silver ₹164.26/g ▼ -3.33% Platinum ₹4,087.25/g ▼ -5.34% Palladium ₹2,839.47/g ▼ -3.78% Rhodium ₹24,507.21/g ▼ -0.58% Copper ₹1,082.05/kg ▼ -4.46% Aluminium ₹244.40/kg ▼ -1.87% Cobalt ₹2,855.27/kg ▼ -0.03% Gallium ₹22,096.10/kg ▼ -0.03% Indium ₹58,752.64/kg ▼ -4.20% Iron Ore ₹7.72/kg ▼ -0.35% Lead ₹158.84/kg ▼ -0.47% Lithium ₹1,172.50/kg ▲ +3.05% Molybdenum ₹7,759.18/kg ▼ -0.03% Nickel ₹1,363.03/kg ▼ -2.54% Neodymium ₹11,782.45/kg ▼ -0.03% Tin ₹3,970.97/kg ▼ -0.59% Tellurium ₹10,345.57/kg ▼ -0.03% Uranium ₹17,180.43/kg ▼ -0.03% Zinc ₹307.35/kg ▼ -1.35% Crude Oil (Brent) ₹8,694.63/bbl ▼ -0.03% Crude Oil (WTI) ₹7,914.98/bbl ▼ -0.75% Gasoline ₹233.25/gal ▼ -1.73% Natural Gas ₹303.27/MMBtu ▲ +4.30%
Scandium

Friedland's Sunrise Approves a $322 Million Scandium Mine in Australia With US Backing

Outlook: Neutral · November 3, 2026
Friedland's Sunrise Approves a $322 Million Scandium Mine in Australia With US Backing

Sunrise Energy Metals, chaired by Robert Friedland, has approved construction of its $322 million Syerston scandium mine and refinery in Australia. It aims to become the first major primary source of scandium outside China, producing 60 tonnes a year from 2028.

At a glance

  • Sunrise has a conditional commitment of up to $400 million in long-term debt from a US government lender.
  • Construction and commissioning are expected to take 24 months.
  • The mine is planned to run for 32 years, producing scandium oxide over 99.9% pure.

Background

Scandium is a rare metal used in aerospace, defence, fuel cells that power AI data centres and advanced semiconductors. China dominates supply, and Sunrise says Chinese scandium has almost stopped reaching key markets since Beijing imposed critical mineral export controls in 2025.

What happened

Sunrise Energy Metals has approved construction of its Syerston scandium project in New South Wales, MINING.COM and Bloomberg reported on November 2. It expects to start producing high-purity scandium oxide in the second half of 2028, ramping up to 60 tonnes a year.

The project is estimated to cost $322 million, and construction and commissioning should take 24 months.

How it is funded

Sunrise has a conditional commitment for up to $400 million in long-term debt from the US Department of War's Office of Strategic Capital. It had A$148.1 million in available cash at September 30.

"Our decision to proceed with development of the Syerston Scandium Project follows extensive technical development, engineering, permitting and commercial engagement," said Friedland, Sunrise's chairman.

What it means

Western economies are looking for scandium supply outside China, and demand is expected to grow through the decade in aerospace, defence, fuel cells for AI data centres and semiconductors. Early works are already under way, including a water pipeline that broke ground on October 9.

Syerston will process 64,000 tonnes of ore a year and is planned to run for 32 years. Sunrise is also studying an expansion beyond 60 tonnes a year, depending on customer demand and financing.

Our read

Outlook: neutral. Syerston would add the first major scandium supply outside China, but output is not due until 2028.

What to watch

  • Final terms of the conditional US government debt.
  • Construction progress towards first output in the second half of 2028.
  • Offtake agreements with aerospace and defence buyers.

For information only, not investment advice.

Detailed analysis

Timeline

  • 2026-10-09: A water pipeline for Syerston breaks ground.
  • 2026-11-02: Sunrise approves construction of the Syerston scandium project.

Supply Drivers

Syerston would produce 60 tonnes a year of scandium oxide from the second half of 2028.

Government Policies

A US government lender has offered conditional debt of up to $400 million.

What could lift prices

  • Chinese scandium has almost stopped reaching key markets since 2025 export controls, Sunrise says.
  • Demand is expected to grow in aerospace, defence and fuel cells.

What could weigh on prices

  • A new 60-tonne-a-year supply source outside China is coming.
  • Sunrise is studying an expansion beyond 60 tonnes a year.

Country impact

CountryImpactReason
AustraliaMediumA scandium mine and refinery will be built in New South Wales.
United StatesMediumA US government lender is backing the project with conditional debt.

Industry impact

IndustryEffectReason
Aerospace & DefencePositiveMakers could gain a scandium source outside China.

Who gains, who loses

  • Aerospace and defence manufacturers: They could secure scandium supply that does not depend on China.
  • Chinese scandium suppliers: A major new source outside China is moving into construction.

Other ways this could play out

  • If construction stays on schedule, Syerston could supply scandium from the second half of 2028.
  • If the US debt is not finalised, funding could take longer.

Price risks

  • New refineries often take longer than planned to reach full output.
  • Changes in Chinese export policy could affect scandium prices.

Related

Metals scandium

Frequently Asked Questions

A scandium mine and refinery in New South Wales, Australia, planned to produce 60 tonnes of scandium oxide a year from 2028.

About $322 million, with conditional US government debt of up to $400 million available.

It is used in aerospace, defence, fuel cells and advanced semiconductors, and China dominates its supply.

Reporting based on information published by MINING.COM. Analysis and interpretation by MetalsCost.